Renovation of South Pasadena High School’s track is moving quickly, and is expected to be finished ahead of schedule.

The project began on December 15, and was scheduled for completion by February 4. But ahead-of-schedule construction has pushed the projected completion date to January 23, according to Athletic Director Gregorio Luna.

“I am amazed with the progress,” Luna said. “Everything is going extremely well.”

The project has closed the stadium, leaving the boys and girls soccer team without a home field for a portion of their seasons. The varsity teams are playing their home games on the baseball outfield, while JV are playing their home games on the South Pasadena Middle School field.